Multiple Choice
Only when the requirements are sufficiently detailed, suppliers feel comfortable using a:
A) fixed- price contract.
B) cost- reimbursable contract.
C) incentive- based contract.
D) time- and- materials contract.
Correct Answer:

Verified
Correct Answer:
Verified