menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Systems Project Management
  4. Exam
    Exam 1: Lntroduction to Project Management
  5. Question
    A Technique That Uses Optimistic, Pessimistic, and Realistic Time to Calculate
Solved

A Technique That Uses Optimistic, Pessimistic, and Realistic Time to Calculate

Question 102

Question 102

Short Answer

A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is called ___________.

Correct Answer:

verifed

Verified

program ev...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q95: Which activity is NOT part of the

Q96: Project management process groups include initiating, planning,

Q97: The project sponsor has the responsibility of

Q98: The project management core area including organizational

Q99: A method used for determining the sequence

Q100: To be considered a success, a project

Q101: A planned undertaking of related activities to

Q103: During the _process, all paper work is

Q104: A chart showing the start and end

Q105: The entities that have a vested interest

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines