menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Systems Project Management
  4. Exam
    Exam 13: Understanding Task Dependencies, Resource Allocation, and Progress Tracking
  5. Question
    In the Earned Value Report, Microsoft Project Uses________ to Indicate
Solved

In the Earned Value Report, Microsoft Project Uses________ to Indicate

Question 29

Question 29

Multiple Choice

In the earned value report, Microsoft Project uses________ to indicate the planned value (PV) .


A) BCWS
B) BCWP
C) ACWS
D) ACWP

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q24: In Microsoft Project, you can only use

Q25: In the tracking Gantt chart view, the

Q26: The first step to manage progress of

Q27: "Always track by entering the actual work

Q28: Which dependency option is NOT available in

Q30: The default view in Microsoft Project is

Q31: Before entering resources, you should identify the

Q32: Once a project is saved as a

Q33: Major tasks in a project can be

Q34: What is NOT among the calendar templates

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines