    A Liquidated Damages Clause Will Be Enforced by the Court
Solved

A Liquidated Damages Clause Will Be Enforced by the Court

Question 43

Question 43

True/False

A liquidated damages clause will be enforced by the court if at the time the contract is made the amount is a genuine pre-estimate of the damages that a Court would award.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q38: Monte Miller buys a television from Discount

Q39: Which of the following will be used

Q40: The key difference between a deposit and

Q41: In the two cases of Trigg and

Q42: There is a strong presumption that the

Q44: Which of the following is NOT a

Q45: A clause in an agreement states: "There

Q46: In a contract between Samsung and Best

Q47: Which of the following would a company

Q48: Which of the following statements accurately states

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines