Multiple Choice
_____________would be the best tool to use if you were the project manager assigned to building a new office complex.
A) A process layout
B) A PERT Network chart
C) A break- even analysis
D) A Gantt chart
Correct Answer:

Verified
Correct Answer:
Verified