Multiple Choice
A_____________ is a flowchart- like diagram that depicts the sequence of activities needed to complete a project and the time or costs associated with each activity.
A) TQM diagram
B) PERT network
C) break- even analysis
D) Gantt chart
Correct Answer:

Verified
Correct Answer:
Verified