Multiple Choice
Which of the following is the consequence of an unpaid subcontractor failing to file his lien on time? The owner had contracted with the general contractor who in turn had contracted with this subcontractor.
A) He can submit documents giving his reason and he will be allowed to file the lien late.
B) He will lose all of his remedies.
C) He will lose his right to place a charge against the owner's property, but he can sue the owner directly for the amount owed him, because his work and materials went into the owner's house.
D) He would lose his right to place a charge against the owner's property, but he can sue the contractor on the contract.
E) He loses his right to claim against the building but can sue the owner of the property directly.
Correct Answer:

Verified
Correct Answer:
Verified
Q69: Explain how the rights of the creditors
Q70: Which of the following is false with
Q71: Which one of the following is true
Q72: You are in debt to three creditors
Q73: Why is the distinction between a guarantee
Q75: Consider the following statements about the use
Q76: If no builders' liens are registered within
Q77: Discuss situations in which a secured creditor
Q78: Explain what is meant by a "chose
Q79: In Re Fancy, a businessman knew that