Complete the ES, EF, LS, LF chart and be prepared to answer questions below.
Find the slack on all events
a. Give EF of Activity F
b. Give ES of Activity G
c. Give LS of Activity F
d. Give LF of Activity B
e. Give slack for Activity D
f. Give length of critical path
Correct Answer:

Verified
a. 8
b. 1...View Answer