Senior management often justify reducing the time schedules for system projects by
A) saying the workers lack proper motivation.
B) saying the tighter schedules make workers work more efficiently.
C) saying that angry employees work better.
D) saying they want to look good to their bosses.
E) saying they want to reduce the budget.
Correct Answer:

Verified