    Subtasks Are Created and Undone Using The________ Keys
Solved

Subtasks Are Created and Undone Using The________ Keys

Question 36

Question 36

Multiple Choice

Subtasks are created and undone using the________ keys.


A) shift
B) tab
C) ctrl
D) alt
E) arrow

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q3: A Tracking Gantt allows a project manager

Q9: You can create subtasks within the tasks

Q24: The resource usage view would allow a

Q31: MS Project is best described as a(n)

Q32: Dependencies are reflected in the _screen.

Q34: MS Project allows a project manager to

Q35: The default view of MS Project is

Q37: It is _ to show all the

Q39: All project management begins with an understanding

Q41: MS Project stores information about<br>A)budgets<br>B)schedules<br>C)resources<br>D)tasks<br>E)all of the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines