Multiple Choice
Assume that a government received a $5,000,000 expenditure-driven grant in Year 1 for a project that was expected to take three years to complete. Further assume that qualifying expenditures for the project, which actually took four years to complete, were as follows: Year 1-$1,000,000; Year 2-$2,500,000; Year 3-$1,000,000; Year 4-$400,000. Assuming the grant receivable is available in each period, the government should report grant revenues in Year 2 in the amount of
A) $1,000,000.
B) $2,500,000.
C) $3,500,000.
D) $5,000,000.
Correct Answer:

Verified
Correct Answer:
Verified
Q42: Moore County is developing a new
Q43: Which of the following expenditures
Q44: A Capital Projects Fund may report a
Q45: Which of the following transactions would not
Q46: The city is installing curbs and sidewalks
Q48: If a governmental entity issued a six-month,
Q49: A governmental entity is funding a capital
Q50: Ledford County issued $2,000,000 of general obligation
Q51: Which of the following is true?<br>A) A
Q52: The City of Bamberg, which has a