Multiple Choice
If a company uses the same discount rate for evaluating all projects,which of the following results is likely?
A) Accepting poor,high-risk projects.
B) Rejecting good,low-risk projects.
C) Accepting only good,low risk projects.
D) Accepting no projects.
E) Answers a and b are both correct.