Essay
The following ILP is being solved by the branch and bound method. You have been given the initial relaxed IP solution. Complete the entries for the 3 nodes and label the arcs when you branch on X2.
Initial solution
X1 = 5.0
X2 = 7.5
Obj = 550
Correct Answer:

Verified
Correct Answer:
Verified