Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
-Which of the following correctly describes the focus of the Critical Path Method (CPM) ?
A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Exhibit 15.3<br>The following questions are based on
Q5: Exhibit 14.13<br>The following questions use the information
Q6: Exhibit 14.13<br>The following questions use the information
Q7: Exhibit 15.1<br>The following questions employ the AON
Q8: Exhibit 15.4<br>The following questions are based on
Q10: One of PERT's bold assumptions is that<br>A)
Q11: Exhibit 15.3<br>The following questions are based on
Q12: Exhibit 15.2<br>The following questions employ the AON
Q13: Exhibit 14.13<br>The following questions use the information
Q14: Exhibit 15.1<br>The following questions employ the AON