Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below. Exhibit 15.2 The following questions employ the AON network and completed spreadsheet below.     -Which of the following correctly describes the focus of the Critical Path Method (CPM) ? A)  To order activities in a project in terms of their completion time to facilitate scheduling of the activities. B)  To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule. C)  To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable. D)  To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities. Exhibit 15.2 The following questions employ the AON network and completed spreadsheet below.     -Which of the following correctly describes the focus of the Critical Path Method (CPM) ? A)  To order activities in a project in terms of their completion time to facilitate scheduling of the activities. B)  To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule. C)  To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable. D)  To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
-Which of the following correctly describes the focus of the Critical Path Method (CPM) ?


A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.