What is the formula for the earliest finish time for activity i?


A) EFTi = ESTi + ti
B) EFTi = EFTj + tj
C) EFTi = EFTi-1 + ti
D) EFTi = ESTi - ti

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: Exhibit 15.2<br>The following questions employ the AON

Q32: Exhibit 15.5<br>The following questions use the information

Q55: If the following project must be

Q60: <br>Consider the CPM network for the following

Q61: <br>The following questions are based on the

Q62: <br>The following questions are based on the

Q64: The critical path is the _ path

Q69: Exhibit 15.2<br>The following questions employ the AON

Q73: Exhibit 14.13<br>The following questions use the information

Q78: Exhibit 14.13<br>The following questions use the information

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines