Multiple Choice
If the following project must be completed by day 18 at minimum cost how do we change the LP model?
A) Enter 18 in cell E14.
B) Add a constraint that E14 18.
C) Make cell E14 the target cell.
D) Add a constraint that E14 = 18.
Correct Answer:

Verified
Correct Answer:
Verified