Essay
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
Correct Answer:

Verified
Correct Answer:
Verified
Q1: <br>The following questions employ the AON network
Q12: Exhibit 15.2<br>The following questions employ the AON
Q23: Exhibit 15.1<br>The following questions employ the AON
Q26: Exhibit 15.5<br>The following questions use the information
Q32: Exhibit 15.5<br>The following questions use the information
Q35: Slack for activity I is computed as<br>A)LFT<sub>i
Q48: Exhibit 15.2<br>The following questions employ the AON
Q52: What formula should go in cell I5
Q56: Which activities have slack in the following
Q73: Exhibit 14.13<br>The following questions use the information