For a Project with Uncertain Activity Times, the Probability of Project

Question 20

Multiple Choice

For a project with uncertain activity times, the probability of project completion exceeding the expected time calculated for the critical path is:


A) 25 percent.
B) 50 percent.
C) 75 percent.
D) none of the above.