Multiple Choice
Which one of the following is not an objective of activity crashing?
A) reduce the total cost of completing a project.
B) complete a project in less time than normally expected.
C) create multiple critical paths.
D) prepare a contract bid.
Correct Answer:

Verified
Correct Answer:
Verified