(A) What Is the Expected Completion Time (In Months) from Now

Question 80

Short Answer

(A) What is the expected completion time (in months) from now for this project?
(B) How much variability (in months) exists around the expected value found in (A)?

Correct Answer:

verifed

Verified

(A) E(X) = 3.875 mon...