Thurston Company's budget allows for one pound of material to be used for each unit produced. The budget indicates that the material costs $2.50 per pound. Actual units produced totaled 8,000. The company used a total of 8,200 pounds of material at an actual cost of $2.40 per pound. There were no beginning or ending inventories of raw materials. The input price and input quantity variances, respectively, would be: