Multiple Choice
For what reason(s) might the overhead volume variance occur?
I.Overhead cost control is poor.
II.The actual activity level was less than estimated.
III.The expected production level was greater than budgeted.
A) I and II
B) II and III
C) I and III
D) I, II, and III
Correct Answer:

Verified
Correct Answer:
Verified