Multiple Choice
At the start of 2014, Capital Cemetery determined its standard labor cost to be 2.5 hours for each cemetery plot prepared at $14.00 per hour. The budget for variable overhead was $8 per plot and budgeted fixed overhead was $15,000 for the year. Overhead is applied based on the number of plots prepared. The company expects to prepare 5,000 plots during 2014. During 2014, the actual cost of labor was $14.30 per hour. Capital prepared 4,900 cemetery plots requiring 11,700 direct labor hours. Actual overhead for the year was $52,100. How much is the overhead volume variance?
A) $1,800 favorable
B) $300 unfavorable
C) $2,100 favorable
D) $800 favorable
Correct Answer:

Verified
Correct Answer:
Verified
Q23: Harris Manufacturing produces white sauce. It
Q31: Rumington Popcorn uses a standard cost system
Q32: Which of the following variances is not
Q60: If the material quantity variance is favorable,
Q90: The labor rate variance is also known
Q92: The controllable variable overhead variance is inappropriately
Q112: Which one of the following is true
Q120: What will result if the actual overhead
Q131: Into what components is the manufacturing overhead
Q135: If the controllable overhead variance is favorable,