When Should an Estimated Total Loss on a Construction Project

Question 58

Short Answer

When should an estimated total loss on a construction project be recognized under the percentage of completion method and the completed contract method, respectively?  Percentage of completion Completed contracta.In year of discovery  In year of discoveryb. Over life of contractIn year of discovery c.In year of discovery  In year of completion d.Over life of contract In year of completion \begin{array} { l } &\text { Percentage of completion} &\text { Completed contract}\\a. &\text {In year of discovery } &\text { In year of discovery}\\ b.&\text { Over life of contract} &\text {In year of discovery }\\c. &\text {In year of discovery } &\text { In year of completion }\\d. &\text {Over life of contract } &\text {In year of completion }\\\end{array}