Multiple Choice
Venice Company has two production departments, Mixing and Finishing, served by one maintenance department.Budgeted fixed costs for the maintenance department were $30,000, and the variable cost per labor hour was $5.00.Other relevant data are as follows: *in labor hours Actual maintenance department costs were $36,000 fixed and $100,000 variable.The amount of variable maintenance costs allocated to the Finishing Department should be _____.
A) $42,000
B) $48,000
C) $37,500
D) $45,000
Correct Answer:

Verified
Correct Answer:
Verified
Q51: Allocating fixed costs based on long-range plans
Q52: Type 3 allocations are cost that flow
Q53: Eisenhower Company manufactures two models of
Q55: Tardes Company has two service departments,
Q57: The use of cost drivers such as
Q58: McClain Company has two departments, Hot
Q59: In the step-down method, the first service
Q60: _ should be used to allocate fixed
Q61: Alleluia Company has two service departments,
Q114: Joint costs are not allocated to a