_____ Should Be Used to Allocate Variable Costs

Question 45

Multiple Choice

_____ should be used to allocate variable costs.


A) Budgeted unit rate x total budgeted units planned to be used
B) Actual unit rate x total budgeted units planned to be used
C) Budgeted unit rate x actual units used
D) Actual unit rate x actual units used

Correct Answer: