Multiple Choice
Seinfeld Company planned to produce 12,000 units.This level of activities required 20 set-ups at a cost of $18,000 plus $500 per set-up.Actual sales were 10,000 units, requiring 15 set-ups and 12,000 machine hours.Actual set-up cost was $26,000._____ is the flexible-budget variance for set-ups.
A) $2,000 favorable
B) $2,000 unfavorable
C) $500 favorable
D) $500 unfavorable
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Actual quantity used - standard quantity allowed)
Q10: A favorable expense variance is when budgeted
Q35: Why should a budgeted cost not be
Q37: Hut Company's variable selling and administrative cost
Q38: Green Company planned to produce 12,000 units.Processing
Q40: John Company's master budget sales were $225,000.Actual
Q41: The following data are for Bob
Q42: The flexible budget is identical to the
Q43: Performance report is a generic term that
Q44: The quantity variance can be calculated by