Multiple Choice
Identify which statement below would not be a possible reason for a variance between a flexible budget and actual results.
A) Material prices were different than expected.
B) Labor prices were different than expected.
C) The actual volume of activity was different than expected.
D) The amount of labor used per unit of output was different than expected.
Correct Answer:

Verified
Correct Answer:
Verified