Short Answer
The difference between actual input prices and expected input prices multiplied by the actual quantity of inputs used
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q22: A _ is most likely to be
Q23: Activity-level variances plus flexible-budget variances equals _.<br>A)total
Q24: If the flexible?budget variance was $6,000 favorable,