Ethan Steel, Inc ​
Shipping Details (With Per-Unit Shipping Cost)

Question 50

Essay

Ethan Steel, Inc. has two factories that manufacture steel components for four different rail projects. The demand for the steel components for the four projects, Project A, Project B, Project C, and Project D, are 3220, 3675, 4125, and 2975, respectively. The shipping details are as below.
Production Details:  Factory  Maximum  Capacity 1650028500\begin{array} { l c } \text { Factory } & \begin{array} { c } \text { Maximum } \\\text { Capacity }\end{array} \\\hline 1 & 6500 \\2 & 8500\end{array}
Shipping Details (with per-unit shipping cost):  Project  Factory  A  B  C  D 1$7$7$8$42$6$5$7$3\begin{array} { l c c c c } & { \text { Project } } \\\hline \text { Factory } & \text { A } & \text { B } & \text { C } & \text { D } \\\hline 1 & \$ 7 & \$ 7 & \$ 8 & \$ 4 \\2 & \$ 6 & \$ 5 & \$ 7 & \$ 3\end{array} What is the optimal (cost minimizing) distribution plan for this transportation problem?

Correct Answer:

verifed

Verified

Let x11: number of steel components shippe...