The Sandoval Company has four process engineers that are each able to process 1,500 design changes. Last year 5,250 design changes were produced by the four engineers. Each engineer is paid $60,000 per year. Calculate the activity rate per change order.
A) $4 per change order
B) $10 per change order
C) $40 per change order
D) $15 per change order
Correct Answer:

Verified
Correct Answer: