Which of the Following Items Is Required for Cost Assignment

Question 165

Multiple Choice

Which of the following items is required for cost assignment to product i under Duration-Based Costing (DBC) ?


A) The overhead cost per unit of product i
B) The standard capacity for product i
C) The cycle time for each product i
D) The total time for all secondary production activities of product i