Multiple Choice
Which of the following is a difference between a job-order costing system and a process-costing system?
A) A job-order costing system accumulates costs by department, while a process costing-system accumulates costs by job.
B) A job-order costing system is used only by manufacturing firms, while a process-costing system is used by both manufacturing firms and service firms.
C) A job-order costing system uses a single work-in-process account, while a process-costing system has a work-in-process account for every process.
D) A job-order costing system uses cost-sheets for assigning labor costs, while a process-costing system uses time tickets for assigning labor costs to processes.
Correct Answer:

Verified
Correct Answer:
Verified
Q141: Golden Ring Company produces two types
Q142: Transferred-in goods, must be converted to the
Q143: Mountainside Industries manufactures specialized plastic boxes
Q144: The unit-costing method that excludes prior-period work
Q145: The cost flows for a process-costing system
Q147: If a spoilage is normal (expected), the
Q148: Mannassass Company manufactures chairs. The following
Q149: The costing system that uses job-order procedures
Q150: Xanadu Company manufactures a product that
Q151: When materials are not added uniformly using