The Static Budget Variance for Materials Is $250 F and the Budgeted

Question 189

Multiple Choice

The static budget variance for materials is $250 F and the budgeted cost for materials is $52,000. If the budgeted volume is 13,000 and the actual volume is 13,500, then the flexible budget variance is


A) $2,250 F.
B) $3,050 F.
C) $2,050 F.
D) $1,850 F.

Correct Answer: