Villanova, Inc $5,000+$0.05\quad \$ 5,000 + \$ 0.05 Per Machine Hour
Machining

Question 85

Multiple Choice

Villanova, Inc., has done a cost analysis for its production of rubber stamps. The following activities and cost drivers have been developed: Activity
Cost Formula
Design $5,000+$0.05\quad \$ 5,000 + \$ 0.05 per machine hour
Machining $25,000+$0.01\quad \$ 25,000 + \$ 0.01 per machine hour
Setups $35\quad \$ 35 per batch
Purchasing $50+$15\quad \$ 50 + \$ 15 per purchase order
Following are the actual costs of producing 35,000 rubber stamps: 1,000 machine hours; 5 batches; 30 purchase orders
 Design $5,080 Machining ? Setups ? Purchasing $600\begin{array} { l r } \text { Design } & \$ 5,080 \\ \text { Machining } & ? \\ \text { Setups } & ? \\ \text { Purchasing } & \$ 600 \end{array}
The following variances were given in the activity performance report:
Design
?
Machining $40 F\quad \$ 40 \mathrm {~F}
Setups $15 F\quad \$ 15 \mathrm {~F}
Purchasing
? What is the activity variance for purchasing?


A) $500 U
B) $100 U
C) $50 U
D) none of these