The following information relates to Lancashire Manufacturing: To produce a unit of product: There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes.
How long would it take to process the first unit of a 20-unit batch under a cellular manufacturing setup?
A) 21 minutes
B) 12 minutes
C) 19 minutes
D) 60 minutes