Multiple Choice
The following information is available for Woodside Furniture Company, which sells two products: There are 200 hours available in the plant and 200 square feet of metal available per operating period. The constraint equation representing processing time available is
A) 4X + 6Y ? 200.
B) 4X + 6Y ? 200.
C) 30X + 18Y ? 200.
D) 4X + 6Y ? 400.
Correct Answer:

Verified
Correct Answer:
Verified