Multiple Choice
company is considering a new project.The CFO plans to calculate the project's NPV by estimating the relevant cash flows for each year of the project's life (i.e., the initial investment cost, the annual operating cash flows, and the terminal cash flow) , then discounting those cash flows at the company's overall WACC.Which one of the following factors should the CFO be sure to INCLUDE in the cash flows when estimating the relevant cash flows?
A) All sunk costs that have been incurred relating to the project.
B) All interest expenses on debt used to help finance the project.
C) The investment in working capital required to operate the project, even if that investment will be recovered at the end of the project's life.
D) Sunk costs that have been incurred relating to the project, but only if those costs were incurred prior to the current year.
E) Effects of the project on other divisions of the firm, but only if those effects lower the project's own direct cash flows.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: primary advantage to using accelerated rather than
Q8: Which of the following factors should be
Q14: company, RMU Inc., is considering a new
Q15: use of accelerated versus straight-line depreciation causes
Q16: Taussig Technologies is considering two potential projects,
Q18: can identify the cash costs and cash
Q29: cash flow estimation, the existence of externalities
Q32: Although it is extremely difficult to make
Q37: Sensitivity analysis measures a project's stand-alone risk
Q57: Liberty Services is now at the end