Solved

Given the Following Network with Activities and Times Estimated in Days

Question 22

Essay

Given the following network with activities and times estimated in days,  Given the following network with activities and times estimated in days,    \begin{array}{l} \text { Most }\\ \begin{array} { c c c c }  \text { Activity } & \text { Optimistic } & \text { Probable } & \text { Pessimistic } \\ \hline \text { A } & 2 & 5 & 6 \\ \text { B } & 1 & 3 & 7 \\ \text { C } & 6 & 7 & 10 \\ \text { D } & 5 & 12 & 14 \\ \text { E } & 3 & 4 & 5 \\ \text { F } & 8 & 9 & 12 \\ \text { G } & 4 & 6 & 8 \\ \text { H } & 3 & 6 & 8 \\ \text { I } & 5 & 7 & 12 \\ \text { J } & 12 & 13 & 14 \\ \text { K } & 1 & 3 & 4 \end{array} \end{array}   a.What are the critical path activities? b.What is the expected time to complete the project? c.What is the probability the project will take more than 28 days to complete?  Most  Activity  Optimistic  Probable  Pessimistic  A 256 B 137 C 6710 D 51214 E 345 F 8912 G 468 H 368 I 5712 J 121314 K 134\begin{array}{l}\text { Most }\\\begin{array} { c c c c } \text { Activity } & \text { Optimistic } & \text { Probable } & \text { Pessimistic } \\\hline \text { A } & 2 & 5 & 6 \\\text { B } & 1 & 3 & 7 \\\text { C } & 6 & 7 & 10 \\\text { D } & 5 & 12 & 14 \\\text { E } & 3 & 4 & 5 \\\text { F } & 8 & 9 & 12 \\\text { G } & 4 & 6 & 8 \\\text { H } & 3 & 6 & 8 \\\text { I } & 5 & 7 & 12 \\\text { J } & 12 & 13 & 14 \\\text { K } & 1 & 3 & 4\end{array}\end{array}
a.What are the critical path activities?
b.What is the expected time to complete the project?
c.What is the probability the project will take more than 28 days to complete?

Correct Answer:

verifed

Verified

a. and b. \[\begin{array} { c c c }
\te ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions