Multiple Choice
Reference: 06-04
In the O'Donnell Manufacturing Company, at an activity level of 80,000 machine hours, total overhead costs were
$223,000. Of this amount, utilities were $48,000 (all variable) and depreciation was $60,000 (all fixed) . The balance of the overhead cost consisted of maintenance cost (mixed) . At 100,000 machine hours, maintenance costs were $130,000.
Assume that all of the activity levels mentioned in this problem are within the relevant range.
-If 110,000 machine hours of activity are projected for next period, total expected overhead cost would be?
A) $256,000.
B) $306,625.
C) $242,500.
D) $263,500.
Correct Answer:

Verified
Correct Answer:
Verified
Q37: The difference between sales revenues and the
Q39: Which of the following statements is most
Q39: Modern technology is causing shifts away from
Q40: Contribution margin is the difference between total
Q41: Given the cost formula Y = $17,500
Q43: Given the cost formula Y = $12,000
Q44: An advantage of the least-squares regression method
Q45: Actual maintenance costs for a movie
Q47: Reference 06-14<br>Macklemore Corporation has identified the
Q115: The planning horizons for committed fixed costs