Question 102

Multiple Choice

Buckeye Company has provided the following data for maintenance cost:  Prior Year  Current Year  Machine hours 12,50015,000 Maintenance cost $27,000$31,000\begin{array} { | l | l | l | } \hline & \text { Prior Year } & \text { Current Year } \\\hline \text { Machine hours } & 12,500 & 15,000 \\\hline \text { Maintenance cost } & \$ 27,000 & \$ 31,000 \\\hline\end{array} The best estimate of the cost formula for maintenance is?


A) $27,000 per year plus $1.60 per machine hour.
B) $21,625 per year plus $0.625 per machine hour.
C) $7,000 per year plus $0.625 per machine hour.
D) $7,000 per year plus $1.60 per machine hour.