Manchester Ltd Actual Manufacturing Overhead Costs Incurred in December Were £31,000

Question 10

Essay

Manchester Ltd. uses a job-order costing system and a predetermined overhead rate based on machine hours.
At the beginning of the year, the company estimated manufacturing overhead for the year would be £135,000 and 9,000 machine hours would be used.
The following information pertains to December of the current year:  Job No.  Job No.  Job No. 380381382 Totals  Work in process, December 1 £8,000£13,000£19,000£40,000 December production activity:  Materials requisitioned £2,000£2,400£3,600£8,000 Direct labour costs £1,200£1,800£2,000£5,000 Machine hours 4007009002,000\begin{array}{lrrrr}&\text { Job No. } & \text { Job No. } & \text { Job No. } & \\&380 & \underline{381} & \underline{382} & \text { Totals } \\\hline\text { Work in process, December 1 } & £ 8,000 & £ 13,000 & £ 19,000 & £ 40,000 \\\text { December production activity: } & & & & \\\text { Materials requisitioned } & £ 2,000 & £ 2,400 & £ 3,600 & £ 8,000 \\\text { Direct labour costs } & £ 1,200 & £ 1,800 & £ 2,000 & £ 5,000 \\\text { Machine hours } & 400 & 700 & 900 & 2,000\end{array} Actual manufacturing overhead costs incurred in December were £31,000.
a.Compute the predetermined overhead application rate.
b.Determine the total cost associated with each job.