Multiple Choice
July Manufacturing uses an average of 150 units per day, although usage can run as high as 175 units per day. If July maintains a recommended amount of safety stock and lead time is three days, what is July's reorder point?
A) 450 units
B) 510 units
C) 525 units
D) 600 units
Correct Answer:

Verified
Correct Answer:
Verified