Multiple Choice
Fortensky Construction planned to produce 275,000 units using 34,375 machine hours. Actual output was 290,000 units using 37,425 machine hours. Fortensky's volume variance
A) was favourable.
B) was unfavourable.
C) was zero.
D) cannot be determined from the information given.