The static budget variance for materials is £200 F and the budgeted cost for materials is £52,000. If the budgeted volume is 13,000 and the actual volume is 13,500, then the flexible budget variance is
A) £2,200 F.
B) £3,000 F.
C) £2,000 F.
D) £1,800 F.
Correct Answer:

Verified
Correct Answer:
Verified