Multiple Choice
Figure 16-2
Glenn, SA., has done a cost analysis for its production of T-shirts. The following activities and cost drivers have been developed: Following are the actual costs of producing 75,000 T-shirts: 5,000 machine hours; 10 batches; 20 purchase orders
-Refer to Figure 16-2. What is the budget variance for inspection in an activity-based performance report?
A) £1,000 F
B) £2,000 F
C) £3,000 F
D) none of the above
Correct Answer:

Verified
Correct Answer:
Verified