Multiple Choice
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications) . Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Activity drivers for each activity have been identified and their practical capacities listed: The costs of facility-level activities are assigned using machine hours.
-Refer to Figure 11-2. What is the cost pool rate for the facility-level activities?
A) £80.00 per machine hour
B) £13,500.00 per setup
C) £17.20 per machine hour
D) £97.20 per machine hour
Correct Answer:

Verified
Correct Answer:
Verified
Q27: If activity-based costing is used, electricity usage
Q28: Figure 11-4<br>The Overdale plant has two
Q29: Figure 11-5<br>Granite, SA., has identified the
Q30: Riley, SA., has identified the following
Q31: Figure 11-3<br>Moss Ltd. has the following
Q33: Figure 11-2<br>Owens Ltd. produces specially machined
Q34: Committed resources are<br>A)hard to purchase.<br>B)purchased precisely at
Q35: Books Company manufactures and sells two
Q36: Ernest, SA., has identified the following
Q37: Hill Manufacturing uses an activity-based costing