Multiple Choice
Consider the following project data: (1) A $500 feasibility study will be conducted at t = 0.
(2) If the study indicates potential, the firm will spend $1,000 at t = 1 to build a prototype. The best estimate now is that there is an 80 percent chance that the study will indicate potential, and a 20 percent chance that it will not.
(3) If reaction to the prototype is good, the firm will spend $10,000 to build a production plant at t = 2. The best estimate now is that there is a 60 percent chance that the reaction to the prototype will be good, and a 40 percent chance that it will be poor.
(4) If the plant is built, there is a 50 percent chance of a t = 3 cash inflow of $16,000 and a 50 percent chance of a $13,000 cash inflow.
A) -$35
B) -$12
C) $ 0
D) $12
E) $35
Correct Answer:

Verified
Correct Answer:
Verified
Q60: What is the project's NPV?<br>A) $2,622<br>B) $2,803<br>C)
Q61: Which of the following statements is correct?<br>A)
Q62: California Mining is evaluating the introduction of
Q63: Adams Audio is considering whether to make
Q64: The Unlimited, a national retailing chain, is
Q66: Pierce Products is deciding whether it makes
Q67: Changes in net operating working capital do
Q68: Sensitivity analysis measures the stand-alone risk of
Q69: With the current techniques available, estimating cash
Q70: Using the same risk-adjusted discount rate to