Multiple Choice
__________measure(s) the risk of a capital budgeting project by estimating the NPVs associated with the optimistic, most likely, and pessimistic cash flow estimates.
A) Multiple regression analysis
B) Simulations
C) Risk-adjusted discount rates
D) Sensitivity analysis
Correct Answer:

Verified
Correct Answer: