A Project Which Has a Coefficient of Variation Greater Than

Question 21

Multiple Choice

A project which has a coefficient of variation greater than zero will have a risk-adjusted discount rate


A) less than the risk-free rate of return.
B) greater than the risk-free rate of return.
C) equal to the risk-free rate of return.
D) not related to the risk-free rate of return.

Correct Answer: